NEW QUESTION 11
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)

  • A. In case of external procurement, long-term planning creates purchase requisitions.
  • B. A planning scenario must be released to use it in long-term planning.
  • C. Long-term planning generally is operational planning of important components.
  • D. Reorder point planned materials can be included in long-term planning.

Answer: B,D

 

NEW QUESTION 12
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?

  • A. Total planning online
  • B. Multi-level single-item planning with the "simulation mode" option
  • C. Multi-level single-item planning with the "display material list" option
  • D. Interactive single-item planning for the delayed assembly

Answer: B

 

NEW QUESTION 13
You want to create a new material that - is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly Which standard SAP material type do you use?

  • A. NLAG (non-stock material)
  • B. HAWA (trading good)
  • C. FERT (finished product)
  • D. ROH (raw material)

Answer: D

 

NEW QUESTION 14
The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?

  • A. Activate the freely usable stock in the scope of check.
  • B. Differentiated assignment of two different checking rules in check control.
  • C. Enter an appropriate availability checking rule in the order type.
  • D. Enter an appropriate availability checking group in the material master.

Answer: B

 

NEW QUESTION 15
You select the master data for production orders via production versions.
Which information is contained in a production version?

  • A. The default order type to be used
  • B. The routing and BOM alternatives to be used
  • C. The explosion dates for the routing and BOM
  • D. The control parameters for selecting routings and BOM

Answer: B

 

NEW QUESTION 16
In what sequence are the steps of material requirements planning performed in SAP ECC?

  • A. 1. Net requirements calculation
    2. Lot sizing
    3. Scheduling
    4. Determination of the procurement type
  • B. 1. Net requirements calculation
    2. Lot sizing
    3. Determination of the procurement type
    4. Scheduling
  • C. 1. Calculation of safety stock
    2. Lot sizing
    3. Scheduling
    4. Determination of the procurement type
  • D. 1. Availability check
    2. Lot sizing
    3. Determination of the procurement type
    4. Scheduling

Answer: B

 

NEW QUESTION 17
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)

  • A. General values from work scheduling view in the material master
  • B. User-defined field from operation in task list
  • C. General operation values in task list
  • D. General item values in bill of materials
  • E. Standard value from operation in task list

Answer: B,C,E

 

NEW QUESTION 18
What master data do you need for material replenishment using the KANBAN procedure? (Choose two)

  • A. Control cycle
  • B. Production supply area
  • C. Product cost collector
  • D. Production version
  • E. Rate routing

Answer: A,B

 

NEW QUESTION 19
Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)

  • A. Logistics Information System (LIS)
  • B. Pick list
  • C. Material directory
  • D. Pull list
  • E. Automatic generation of a transport order

Answer: B,D,E

 

NEW QUESTION 20
The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.)

  • A. Goods receipt for a missing part
  • B. Release of the production order
  • C. Creation of the production order
  • D. Goods receipt for the product produced with the order
  • E. Confirmation of the operation that the materials being checked are assigned to

Answer: B,C

 

NEW QUESTION 21
Which of the following statements about consumption are correct? (Choose two)

  • A. Consumption is restructured with the planning run.
  • B. Consumption takes place on the material level between the planned independent requirements and the planned orders.
  • C. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
  • D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.

Answer: C,D

 

NEW QUESTION 22
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following properties for the resulting dependent requirements applies?

  • A. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.
  • B. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
  • C. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.
  • D. In multi-level backward scheduling, dependent requirements are calculated to the exact second.

Answer: C

 

NEW QUESTION 23
Which of the following functions does SAP Supply Chain Management (SCM) offer?

  • A. Product development, safety, quality, and maintenance
  • B. Communication with customers through different interaction channels
  • C. Planning of supply chains across company boundaries
  • D. Optimization of the procurement strategy with the supplier pool

Answer: C

 

NEW QUESTION 24
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).
Which of the following planning file entries for this material are set by the system?

  • A. The BOM explosion indicator
  • B. The BOM explosion and the NETPL planning indicator
  • C. The BOM explosion, the NETCH, and the NETPL planning indicators
  • D. The NETCH and NETPL planning indicators

Answer: C

 

NEW QUESTION 25
What data can be posted directly via the Plant Data Collection (PP-PDC) interface?

  • A. Maintenance notifications
  • B. Goods issues
  • C. Confirmations
  • D. Goods receipts

Answer: C

 

NEW QUESTION 26
From what point can you no longer use the Read PP master data in the production order?

  • A. After assigning the confirmed quantity of a material component due to carrying out a material availability check.
  • B. After the first posting of goods movements or confirmation.
  • C. After printing the order papers.
  • D. From the release of the production order.

Answer: B

 

NEW QUESTION 27
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)

  • A. You can change the strategy group from 10 to 40 for the existing production plan in the material master, and the requirement type for all requirements is changed automatically.
  • B. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements.
  • C. You must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement type for all existing requirements is then changed by the next planning run.
  • D. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.

Answer: B,D

 

NEW QUESTION 28
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default.
However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the system side?

  • A. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.
  • B. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
  • C. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.
  • D. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.

Answer: A

 

NEW QUESTION 29
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)

  • A. Production Scheduling Profile
  • B. Material Master (Finished Product)
  • C. Routing
  • D. Material Master (Component)
  • E. Work Center

Answer: C,D,E

 

NEW QUESTION 30
......


SAP C_TSCM42_67 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Material Requirements Planning (PP-MRP) > 12%

Explore material requirements planning functions.

Production Orders Basics (PP-SFC) 8% - 12%

Apply production order functionality.

Master Data (LDM) 8% - 12%

Set up master data for production planning and manufacturing.

Production Orders Advanced (PP-SFC) > 12%

Configure production order functionality.

Lean Manufacturing (PP-REM, PP-KAB) 8% - 12%

Outline the highlights of repetitive manufacturing and kanban.

Application Overview and Background < 8%

Characterize the interplay of master data, planning, ATP, and production functionality.

Material and Capacity Requirements Planning > 12%

Characterize production-relevant planning functionality.

Basics on SAP Business Processes (E-Learnings) < 8%

Outline the scope of SAP SCM business processes.

Process Orders (PP-PI) < 8%

Identify specific properties of process orders.



C_TSCM42_67 Exam Certification Details:

Component:Production Planning
Cut Score:63%
Level:Associate
Languages:German, English, Japanese
Exam:80 questions
Duration:180 mins
Sub-solution:Product Developmement & Manufacturing
Sample Questions: SAP C_TSCM42_67 Exam Sample Question