[Nov 30, 2021] ActualTestsIT C_TS410_1909 Exam Practice Test Questions (Updated 85 Questions) [Q42-Q63]

Share

[Nov 30, 2021] ActualTestsIT C_TS410_1909  Exam Practice Test Questions (Updated 85 Questions)

Pass SAP C_TS410_1909 Exam Info and Free Practice Test 


SAP C_TS410_1909 Exam Description:

The "SAP Certified Application Associate - Business Process Integration with SAP S/4HANA" certification exam verifies that the candidate has the core knowledge about business processes and their integration in SAP S/4HANA 1909. This certification exam is recommended as an entry level qualification to allow consultants and application users to get acquainted with SAP S/4HANA end-to-end business process fundamentals.


C_TS410_1909 Exam Certification Details:

Sample Questions: SAP C_TS410_1909 Exam Sample Question
Cut Score:66%
Exam:80 questions
Level:Associate
Duration:180 mins
Languages:German, English, Japanese, Russian

 

NEW QUESTION 42
What document, when saved, creates a commitment for an internal order?

  • A. Sales order
  • B. Material document
  • C. Accounting document
  • D. Purchase order

Answer: D

 

NEW QUESTION 43
Which SAP Fiori application types use the SAP HANA data layer directly? There are TWO correct answers for this Question

  • A. Analytical
  • B. Fact sheet
  • C. Web Dynpro
  • D. Transactional

Answer: A,B

 

NEW QUESTION 44
What does Management Accounting provide? There are 2 correct answers to this question.

  • A. Reports that meet accounting standards and principles
  • B. Profitability analysis of market segments
  • C. Account balances for customers and vendors
  • D. Information used for internal areas of responsibility

Answer: B,D

 

NEW QUESTION 45
What is an element that you can assign to the SAP Human Management organizational structure?

  • A. Cost center
  • B. Profitability segment
  • C. Cost element
  • D. Operating concern

Answer: A

 

NEW QUESTION 46
What tasks are performed for legal reporting? There are TWO correct answers for this Question

  • A. Calculate production variances
  • B. Perform inventory valuation
  • C. Track company car costs
  • D. Create a balance sheet

Answer: B,D

 

NEW QUESTION 47
What are the benefits of using a business partner in SAP S/4HANA? There are TWO correct answers for this Question

  • A. You can maintain multiple addresses for an entity
  • B. It provides a harmonized architecture
  • C. General data is unique to each role
  • D. Vendors are managed separately from customers

Answer: A,B

 

NEW QUESTION 48
For what network activity can you plan capacities?

  • A. External activity
  • B. Internal activity
  • C. Service activity
  • D. Cost activity

Answer: C

 

NEW QUESTION 49
In which situation would you create an equipment master record? There are TWO correct answers for this Question

  • A. To report the usage time of an object at a functional location
  • B. To report and track preventive maintenance tasks for an object
  • C. To functionality represent the technical system structures in your company
  • D. To report the effects of usage on the likelihood of damage to the installed equipment

Answer: A,B

 

NEW QUESTION 50
What assigns actual costs to a project?

  • A. Posting a vendor's invoice
  • B. Processing a cost forecast
  • C. Calculating project interest
  • D. Saving a purchase order

Answer: A

 

NEW QUESTION 51
What MRP control parameter defines the scope of a planning run?

  • A. Processing key
  • B. Lot size
  • C. Procurement type
  • D. Planning mode

Answer: A

 

NEW QUESTION 52
What happens when you post a goods issue for a delivery document in sales? There are THREE correct answers for this Question

  • A. A warehouse transfer order is created
  • B. An accounting journal entry is created
  • C. Inventory quantities are updated
  • D. The billing due list is updated
  • E. An invoice is created

Answer: B,C,D

 

NEW QUESTION 53
What can be assigned to a profit center?
There are THREE correct answers for this Question

  • A. Company code
  • B. Asset
  • C. Operating concern
  • D. Organizational unit
  • E. Material

Answer: B,C,E

 

NEW QUESTION 54
What master data records are used in advanced planning? There are THREE correct answers for this Question

  • A. Work center
  • B. Product
  • C. Resource
  • D. Location
  • E. Bill of material

Answer: B,C,D

 

NEW QUESTION 55
What is document splitting used for?

  • A. To summarize CO line items to produce fewer line items
  • B. To summarize G/L postings at the controlling area level
  • C. To fill the segment characteristic in all line items
  • D. To update multiple ledgers for parallel accounting

Answer: C

 

NEW QUESTION 56
What needs to be entered to create a business partner? There are TWO correct answers for this Question.

  • A. Account group
  • B. Business partner role
  • C. Business partner type
  • D. Partner functions

Answer: A,B

 

NEW QUESTION 57
What type of document is generated for an external network activity?

  • A. Sales order
  • B. Purchase requisition
  • C. Reservation
  • D. Planned order

Answer: B

 

NEW QUESTION 58
What does a depreciation area control?
There are TWO correct answers for this Question

  • A. Estimated useful life
  • B. Depreciation start date
  • C. Depreciation accounts
  • D. Asset class

Answer: A,B

 

NEW QUESTION 59
An internal activity price can be assigned to the combination of activity type and which project?

  • A. Work center
  • B. Funds center
  • C. Cost center
  • D. Profit center

Answer: C

 

NEW QUESTION 60
What is an advantage of using stock transport orders instead of stock transfers?

  • A. Ownership transfer is delayed until goods receipt
  • B. The quality inspection is performed by the sending plant
  • C. Goods movements occur in one step
  • D. MRP can be executed to plan the material

Answer: D

 

NEW QUESTION 61
What is required to report on a combination of characteristics, such as customer, product, and region?

  • A. G/L accounts
  • B. Profitability segments
  • C. Profit centers
  • D. Primary cost elements

Answer: B

 

NEW QUESTION 62
You need stock materials to complete your maintenance process. At what steps can a material reservation be created? There are TWO correct answers for this Question

  • A. Release an order
  • B. Settle an order
  • C. Save an order
  • D. Technically complete an order

Answer: A,D

 

NEW QUESTION 63
......


SAP C_TS410_1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Warehouse Management < 8%

Describe warehouse management functionalities.

Lead to Cash Processing 8% - 12%

Explain the lead to cash business process.

Project System 8% - 12%

Explain the project system capabilities.

SAP S/4HANA Basics > 12%

Describe SAP S/4HANA as an enabler for digital transformation, the role of SAP Fiori UX and the concept of organizational structures and master data.

Design to Operate Processing 8% - 12%

Describe the business processes associated with Design-to-Operate.

Core Finance: Management Accounting (CO) > 12%

Analyze the role of management accounting and utilize core functions.

SAP Human Experience Management < 8%

Describe human capital management functionalities and the integration scenarios with Success Factors.

Core Finance: Financial Accounting (FI) < 8%

Describe the role of financial accounting and execute core functionalities.

Source to Pay Processing 8% - 12%

Describe the business processes associated with Purchase-to-Pay.

Enterprise Asset Management (EAM) 8% - 12%

Describe the business process of enterprise asset management.


 

Pass Your SAP Exam with C_TS410_1909 Exam Dumps: https://www.actualtestsit.com/SAP/C_TS410_1909-exam-prep-dumps.html