NEW QUESTION 151
Which of the following will identify the MOST potential project risks?
- A. Benchmarking
- B. Cost-benefit analysis
- C. Past project documentation
- D. Project budget
Answer: C
NEW QUESTION 152
A project manger received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manger do NeXT?
- A. Implement the changes
- B. Gain approval for the changes.
- C. Identify the approval authority
- D. Create an emergency change request.
Answer: A
NEW QUESTION 153
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
- A. Project manager
- B. Sponsor
- C. Project team
- D. Project management office
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 108
NEW QUESTION 154
In which of the fallowing organizational structures would a project manager have the MOST authority?
- A. Balanced matrix
- B. Strong matrix
- C. Functional
- D. Projectized
Answer: C
NEW QUESTION 155
A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?
- A. Share
- B. Mitigate
- C. Avoid
- D. Transfer
Answer: B
Explanation:
References: https://teamweek.com/blog/2017/09/top-project-management-methodologies/
NEW QUESTION 156
Team members in a projectized organization are released at the end of a project and placed on the "bench". Which of the following should the benched team members do NEXT?
- A. Find a new project.
- B. Report to the project manager.
- C. Contact the project sponsor.
- D. Check in with a functional manager.
Answer: D
NEW QUESTION 157
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
- A. ETC
- B. CPI
- C. EAC
- D. BAC
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 231
NEW QUESTION 158
A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
- A. a tollgate.
- B. an incident response.
- C. a milestone.
- D. change management.
Answer: C
NEW QUESTION 159
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
- A. Remove email from the distribution list for the monthly status report
- B. Add email to the distribution list for the weekly status report
- C. Immediately send the current weekly status report
- D. Consult the communications plan and act accordingly
Answer: B
NEW QUESTION 160
A project manager who is part of a global team wants to have a team building meeting and decides to Mold a video conference Which of the following is MOST likely to be the main challenge that influences this decision?
- A. Cultural differences
- B. Technology factors
- C. Geographical factors
- D. Language barriers
Answer: B
NEW QUESTION 161
Which of the following documents should be used to provide high-level reporting to key stakeholders?
- A. Dashboard
- B. Communication plan
- C. Statement of work
- D. Project charter
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
NEW QUESTION 162
A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
- A. Cost performance parameter
- B. KPI
- C. Corrective action plan
- D. WBS
- E. Project schedule
Answer: D,E
Explanation:
Reference:
https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false
NEW QUESTION 163
Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
- A. Requirements change
- B. Risk event
- C. Funding change
- D. Timeline change
Answer: D
NEW QUESTION 164
A project team is defining detailed risks. Which of the following project phases is taking place?
- A. Initiation
- B. Monitor and control
- C. Planning
- D. Execution
Answer: C
NEW QUESTION 165
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
- A. Project coordinator and project sponsor
- B. Project champion and project scheduler
- C. Project manager and project scheduler
- D. Project stakeholders and project team
Answer: D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326
NEW QUESTION 166
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance?
(Choose two.)
- A. Add non-project-related items to the agenda.
- B. Provide an agenda before the status meeting.
- C. Add and discuss new agenda items throughout the meeting.
- D. Discard the action items at the conclusion of the meeting.
- E. Adhere to an agenda and scheduled time.
Answer: B,E
NEW QUESTION 167
A project manager is creating the WBS.
In which of the following phases is the project?
- A. Initiation
- B. Planning
- C. Execution
- D. Closing
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,
Indianapolis, 2017, p. 139
NEW QUESTION 168
Which of the following is used to perform a root cause analysis?
- A. Scatter plot
- B. Pareto diagram
- C. Ishikawa diagram
- D. Bar chart
Answer: C
Explanation:
Reference:
http://asq.org/learn-about-quality/cause-analysis-tools/overview/overview.html
NEW QUESTION 169
......