NEW QUESTION 30
Which type of pipelines collect the gas from the transmission system so utility companies can distribute the gas to end users?

  • A. Distribution
  • B. Transmission
  • C. Midstream
  • D. Gathering

Answer: A

 

NEW QUESTION 31
Dehumidification is defined as the removal of moisture vapor from the air to

  • A. provide worker comfort.
  • B. lower its dew point,
  • C. raise its relative humidity.
  • D. lower its temperature

Answer: B

 

NEW QUESTION 32
The cost of qualified Coating Inspection is normally offset by:

  • A. Lower Application Costs
  • B. Lower Safety Enforcement Costs
  • C. Lower Coating Life Cycle Costs
  • D. Lower Supervision Costs

Answer: C

 

NEW QUESTION 33
The Concrete Repair Institute's comparators can be used to assess:

  • A. Compressive and tensile strength prior to coating
  • B. Surface profile prior to coating
  • C. Surface cleanliness prior to coating
  • D. Contamination levels prior to coating

Answer: B

 

NEW QUESTION 34
Inspectors perform tests on linings that they may not perform on exterior coatings because

  • A. linings are more durable than coatings.
  • B. coatings are more durable than linings.
  • C. linings protect the contents and the container.
  • D. coatings are expected to degrade over time.

Answer: C

 

NEW QUESTION 35
The primary purpose of Fireproofing coatings are to provide:

  • A. Explosion resistance
  • B. Preferential fuel for the fire
  • C. fire extinguishing characteristics
  • D. Temporary protection for the structure

Answer: D

 

NEW QUESTION 36
Corrosion is the reverse process of

  • A. flaking.
  • B. steel manufacturing.
  • C. galvanic deterioration.
  • D. hot dipping.

Answer: B

 

NEW QUESTION 37
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.
Your FIRST preferred course of action is to:

  • A. Check to See if the dehumidification equipment is operating correctly
  • B. Advise the coating applicator supervisor of your readings
  • C. Document the readings at the end of the shift
  • D. Call your supervisor

Answer: B

 

NEW QUESTION 38
Inspection and Test plans are developed by referencing:

  • A. The Specification, SDS, relevant Standards and Codes
  • B. The Specification, Application Guidelines, 'Relevant Standards and Codes
  • C. The Specification, Safety Manual, Relevant Standards and Codes
  • D. The Specification, TDS, relevant Standards and Codes

Answer: D

 

NEW QUESTION 39
An Inspection and Test Plan is required when:

  • A. When the Coating Applicator requests one
  • B. When the Inspector requests one
  • C. It is always required
  • D. When the Owner specifies one

Answer: C

 

NEW QUESTION 40
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:

  • A. Use a generally accepted industry standard and to take readings
  • B. Refuse to take readings until an is in place
  • C. Develop your own methodology and proceed take the readings
  • D. Call your supervisor

Answer: A

 

NEW QUESTION 41
Surface preparation methods for Non-ferrous metals are:

  • A. Not required
  • B. The same as for Ferrous metals
  • C. Specific for each type of Non-ferrous metal
  • D. The same for all Non-FetT0us metals

Answer: C

 

NEW QUESTION 42
NACE Standards include:

  • A. a) & b)
  • B. Material Requirements
  • C. Standard Practices
  • D. a) only

Answer: A

 

NEW QUESTION 43
Which product, is used in conjunction with other coatings such as FBE when the lines run through wetlands or a body of water?

  • A. Coal Tar Enamel
  • B. 3-Layet Polyethylene (PE)
  • C. 2-Layet Polyethylene (PE)
  • D. Concrete

Answer: D

 

NEW QUESTION 44
Which concrete smoothing technique involves scrubbing a mixture of cement mortar over the concrete surface using ai cement sack, gunny sack, or sponge rubber float?

  • A. Sacking
  • B. High-pressure water washing
  • C. Stoning
  • D. Acid etching

Answer: A

 

NEW QUESTION 45
You are the NACE Level 2 Inspector on a project where overcoating of galvanized steel is being performed. The specification references SSPC SP 16 as the surface preparation method. At the pre-job meeting operations personnel make it clear that abrasive blasting will not permitted. The Owner's representative asks you what other methods might be used.
Of the options shown below, what would be the preferred option in this situation?

  • A. SP 1 followed by caustic etching
  • B. SP 1 followed by acid etching
  • C. SP 1 followed by SP 3
  • D. SP 1 followed by SP 2

Answer: D

 

NEW QUESTION 46
When performing testing in accordance with ASTM D 2583 the inspector may observe:

  • A. Cohesion failure
  • B. Cold flow or creep
  • C. Adhesion failure
  • D. Glue failure

Answer: B

 

NEW QUESTION 47
......